Yapaldinni Solar PV Plant, Raichur District

Salient Features of the Solar Plant Installed in Raichur District

Capacity

:

3MW Grid Connected

Total Cost

:

42.0 crores

Energy Content

:

4.5 Mu/annum

Technology

:

Solar PV Crystalline

Evacuation System

&Nbsp;

:

Through 11 kv dedicated line   connecting 33KV  Yapaladinni MUSS.

Average Solar  Insolation

:

5.29Kwh per sq.m. per day

EPC Contractor

:

M/s. Bharat Heavy Electricals  Pvt. Ltd., Bangalore

Land Acquired

:

&Nbsp;

15 acres of Govt. Land in Yapaladinni village.   Anchor

Taluk, Raichur District

Date of LOA

:

21.12.2009

Date of Commissioning     

:

07.02.2012

Finance:&Nbsp;This project is financed by KPCL from its internal resources.

MNRE subsidy: : Ministry of New & Renewable Energy, New-Delhi has sanctioned to KPCL Rs 6.58 crores which is 50% of capital cost for 1MW capacity under tail end grid connected scheme of Government of India.  