Tadadi Combined Cycle Power Plant

  • Govt. of Karnataka Vide G.O. No. CI 222 SPI 2009, Bangalore dated 16.11.2009 has accorded approval to establish the 2100 MW Tadadi Gas based Combined Cycle Power Plant in KumtaTaluk, Uttara Kannada District.
  • Estimated cost of the project is ' 9587 Crores and it would generate 15637 MU of energy annually.
  • Pre-feasibility report prepared and submitted to various Departments for obtaining clearances.
  • 400 acres of land acquired from KIADB and possession of the same taken over on 02-06-2010.
  • NOC from Commodore, Naval Base, Karnal received (Airport clearance).
  • Approved TOR received from MoEF, New Delhi on 23-09-2010.
  • Topo graphical Survey completed.
  • The work of carrying out Environmental Impact assessment (EIA) studies is entrusted to M/s SENES Consultants, Hyderabad and the work is in progress. Rapid Environmental Report prepared and submitted to KSPC with a request to carry out public hearing.
  • Detailed Project Report completed.
  • The work of examining the technical and commercial aspects involved in construction of LNG/FSRU and supply of indigenous gas was awarded to M/s.TGE Gas Engineering. The agency has completed the work and submitted the feasibility report, Request for participation (RFP) and Gas supply purchase agreement(GSPA).

The work of carrying out studies related to design & operational parameters for offshore facility, location of cooling water intake and outfall, delineation of HTL-LTL &CRZ clearance, Marine EIA studies, identification & selection of location for single point mooring and pipeline was entrusted to National Institute of Oceanography(NIO). NIO has completed all the works entrusted to them and submitted the reports.


Updated On:15.07.2014 04:40:05