Munirabad Hydro Power Station

  • Government of Karnataka has accorded approval to establish this project vide order no. EN 134 NCE 2010, Bangaloredt. 18.05.2010
  • Environmental clearance for establishment of the project has been accorded by Department of Forest, Ecology and Environment, Government of Karnataka on 11.3.2011
  • LoI issued on 04.02.2012. Agreement executed with M/s ALLONWARD-SSIPL-KR & CO. CONTORTIUM, Chennai, to execute the work at a total cost of ' 36.32 crores.
  • DSPR members have inspected the site and submitted the report. Approval from Irrigation Department and Water Resource Department has been obtained.
  • Site was handed over to M/s ALLONWARD-SSIPL-KR & CO. on 19-02-2013.
  • Host country approval received and CDM validation is under process.